Gateway Garage Story and
Photos by Gene Storm
Anchorage Rental Car Center Continues Airport Growth
|
The Ted Stevens Anchorage International
Airport is a global, national and regional transportation hub
that has experienced substantial growth over the past few years.
That growth has fueled a continuous stream of construction projects,
with the latest being the new $50-million Anchorage Rental Car
Center that is taking shape at the busy airport.
Anchorage-based Neeser Construction
Inc. is building the 464,000-square-foot concrete, four-story
parking structure with an additional 30,000 square feet of structural
steel office and lobby space as a design-build project. The design-build
process has been ongoing for years, according to Wayne Anderson,
project superintendent.
|
"The planning and development
of this project has taken five years," said Anderson. Using
the design-build approach gives all of the parties involved more
flexibility in making design changes along the way, he noted,
adding, "As construction proceeds, the design-build team
is available to expedite unforeseen changes quickly, which is
essential to meeting construction milestones."
The firms participating in the project
with Neeser as the lead are EDS, structural engineer; Koonce Pfeffer
Bettis, architects; EIC Engineers, electrical; Jenstrom Engineering,
mechanical; and Dowl Engineers, providing the civil engineering.
|
|
|
Early Spring Start
Neeser hit the ground on the project in the fall of 2005 by
relocating water, sewer and gas lines and the electrical/telecommunication
ducts that bisected the site. Last fall's civil work was critical
to achieving a workable construction schedule, according to
Anderson.
"This was a key to the early
spring start, which will allow us to complete major concrete
work before freeze-up in the fall of 2006," Anderson said.
Work on the 1,200-car parking structure is scheduled for completion
in June 2007.
Work resumed early this year with
the excavation of approximately 190,000 cubic yards of material,
of which 150,000 cubic yards was hauled off-site and 40,000
cubic yards was saved as useable backfill. The large parking
structure rising from the excavation will feature five ramps,
including three helix ovals that will enter and exit the building.
The building will include on-site fueling and car wash facilities
to service the rental car fleets. An underground tunnel will
take customers from the airport's main terminal to the rental
car facility.
Some 25,000 cubic yards of concrete
will go into the structure. The foundation consists of 72 spread
footings, each containing more than 50 yards of concrete. Retaining
walls and ramps will bring the total to 15,000 yards, with the
remainder going into tension slabs and beams in the top three
floors. More than 2,000 tons of rebar will go into the project.
The gang forms used to shape the
concrete walls are from EFCO Corp. of Des Moines, Iowa. The
post-tensioning Symons Garage Beam System will be used for the
post-tensioned decks and beams. This is a method of reinforcing
concrete with high-strength steel strands typically referred
to as tendons.
The building will come together
under strict seismic guidelines that are in place for Anchorage's
seismic designation, the maximum within the rating system. As
designed, the structure is considered a special ductile concrete
moment frame.
|
|
|
|
A worker places concrete,
pumped by Alaska Concrete Services Inc. using a Putzmeister
pumper, inside post forms.
|
|
|
|
| Fasteners are released from the EFCO form
on a completed section concrete wall. |
|
|
|
| A john Deere 450 dozer spreads fill along
a foundation wall. |
|
|
|
| A Caterpillar CS-563 vibratory
compactor rolls a backfill area. |
|
Project Challenges
Alaska's weather has been a factor in the early spring concrete
work.
"With the weather staying
colder longer than anticipated, we have more heat and cover
costs than normally expected," Anderson said. The other
side of the weather coin is the savings realized on another
project phase.
"The colder and dryer weather
has been an advantage for the civil side in that we have less
maintenance on airport dump sites, and road cleanup is not as
much of an issue at this high-traffic area," Anderson added.
The project's constrained site
presents a unique challenge for construction crews. The site
is ringed on three sides by different airport facilities. The
FAA tower is just to the north, the Alaska Railroad Station
is on the south perimeter, and Concourse C is close by on the
west.
"With all the various activities
that are associated with these facilities, the challenge has
been to keep these folks from being disrupted yet still keep
an aggressive schedule on track," Anderson noted. "The
surprise has been how small a large job site can become in such
a restricted environment."
To help meet the constrained site
challenge, Neeser has carefully planned daily jobsite activities
and coordinated weekly shipping schedules for materials like
rebar and forms that arrive from Seattle. By project completion,
more than 110 trailer loads of rebar and 50 loads of rental
form materials will have been delivered to the site.
A variety of earthmoving and lifting
equipment also is working on-site. The fleet includes two 175-ton
cranes, articulated dump trucks, and several excavators and
dozers. That equipment moves in and about the site in limited
space that also houses construction office trailers and very
tight parking for workers.
|
|
|
| A worker cleans up a concrete footing using
a pneumatic chisel. |
|
Neeser's peak construction workforce
will consist of 180 employees, including carpenters, laborers
and operators. The major subcontractors, ReBar Placement, MegaWatt
Electric and Klebs Mechanical, will bring another 60 workers
on-site.
Many of the projects that have
fueled growth at the airport were part of a 10-year, $350-million
"Gateway Alaska" plan announced by the state of Alaska
in 1997. The plan included nearby highway improvements in addition
to airport expansion and renovations.
The busy airport serves as a major
air crossroads for air freight carriers. It is also the primary
entry point for many visitors to the state and for other Alaskans
coming to Anchorage for business and shopping opportunities.
This combination of travelers makes for a vibrant rental car
market. The new Anchorage Rental Car Center will bring those
services into a convenient, central facility from disparate
locations currently located more distant from the airport.
|
|
|
|