Lower Yukon School District

Marshall, Hooper Bay & Pilot Station, AK

Marshall K-12 School -

Hooper Bay K-12 School - Complex is the winning entry in a design-build competition. The two-story, 73,800 SF facility contains the post library, a large lecture hall, adult education classrooms, and office and support spaces.

Pilot Station Replacement School - The Pilot Station School is a 46,000sf K-12 School with a central M&E Plant built as a separate building of 6,000sf.

 
- Read full profile -

Dena'ina Civic and Convention Center

Anchorage, AK

This 215,000sf convention center located in the heart of downtown Anchorage is the foundation of the growing convention industry in Alaska. The need, and hope for a facility like this had been around for over two decades, and yet it never seemed to get beyond the hope stage.

 
- Read full profile -

188 W. Northern Lights Blvd.

Anchorage, AK

The 188 West Northern Lights Building is a 293,000sf fifteen story building combining 145,000sf on 4 levels parking, 15,000sf of ground level retail space and 133,000sf (9 floors) of Class A office space. The building is located on the corner of Northern Lights Blvd and "C" Street, in the heart of midtown Anchorage.

 
- Read full profile -

Anchorage Rental Car Center

Ted Stevens Anchorage International Airport

The Anchorage Rental Car Center located at Ted Stevens International Airport, Anchorage, Alaska is a design-build project by Neeser Construction that originated through an innovative development process initiated by Venture Development Group.

 
- Read full profile -

McKinnell House / Cares for Kids

Anchorage, AK

In 2002 The Salvation Army approached Neeser Construction, Inc and explained their desire to improve their services for displaced two parent families and single dads with children.

 
- Read full profile -

Aleutian Pribilof Islands Association

Anchorage, AK

This site created extreme challenges for the design build team. Special considerations were met to create a storm water pollution prevention plan that would work. Besides the standard silt fencing, water catching settling ponds were created.

 
- Read full profile -

The Alutiiq Center

Anchorage, AK

Alutiiq Center is a 72,000 sf 5 story class 'A' office building supported by a 56,000 sf, 170 stall parking structure on the same site. The Afognak Native Corporation (ANC) had expanded operation such that they needed a sufficiently sized headquarters building located in Anchorage

 
- Read full profile -

Home Depot Store #8940

Anchorage, AK

This South Anchorage Home Depot was a fast track project. The property is contiguous to a Safeway Store, so Neeser Construction, as the developer, had to meet Safeway's requirements for access and appearance as well as follow Home Depot's criteria.

 
- Read full profile -

Alert Holding and Pallet Processing

Fort Wainwright, AK

The Alert Holding and Pallet Processing Facility (AHPP) was one of several Task Orders issued to NCI under a five year Multi-Award Task Order Contract with the USACE.

 
- Read full profile -

Bristol Bay Building

Anchorage, AK

This fast track design/build project for Bristol Bay Native Corporation was a 68,410 square foot post tension concrete floor structure with a seismic core consisting of a concrete moment frame bearing on continuous single mass slab on grade.

 
- Read full profile -

Community Education Center

Fort Richardson, AK

The Fort Richardson New Community Education Center (COMC) was one of the first design-build Task Orders issued under NCI's five year MATOC contract with the USACE.

 
- Read full profile -

Alaska Psychiatric Institute

Anchorage, AK

The Alaska Psychiatric Institute Replacement Hospital (API) Alaska is the first design/build vertical construction RFP ever issued by the State of Alaska.

 
- Read full profile -

Southwest Region School District

Togiak and Manokotak, AK

The Togiak K-12 New School consists of a 70,000 square foot new K-12 school in the native fishing village of Togiak, Alaska.


The Manokotak K-12 New School Project was a 47,000 square foot new K-12 school in the native fishing village of Manokotak, Alaska

 
- Read full profile -

South Anchorage Area High School

Anchorage, AK

This is a 240,000 square foot facility designed to serve approximately 1,600 students. It is located on 50 acres of naturally wooded slope...

 
- Read full profile -

Dental, Optometry and Behavioral Health Clinic

Anchorage, AK

Neeser Construction Inc. was selected for the project because of their strong background in design-build and their long history of successful projects for South Central Foundation.

 
- Read full profile -

Anchorage Jail

Anchorage, AK

Neeser Construction, Inc. was the low bidder on a 185,000 square foot, 400 bed jail project. However the low bid was in excess of five million over the Municipality's budget.

 
- Read full profile -

Primary Care Center Phase I & II

Anchorage, AK

Phase I - A 39,000 square foot facility was Design/Built as a companion facility to the new Alaska Native Medical Center in Anchorage. The facility was a fast track project with design and construction completed in fourteen months.

 
- Read full profile -

University of Alaska Parking Garage

Anchorage, AK

The UAA Parking Garage was a hard bid competition. Due to design problems, the project was two months behind schedule. To bring the project on schedule the owner requested we accelerate construction instead of extending the completion time.

 
- Read full profile -

Anchorage Downtown Fire Station #1

Anchorage, AK

This is a Design/Build 30,000 square foot masonry and steel building housing a new Municipal Fire Station with a hose drying tower and separate administration building.

 
- Read full profile -

Public Health Lab & Medical Examiner's Facility

Anchorage, AK

A 37,000 square foot concrete and steel structure housing extensive environmental health laboratory facilities as well a coroner's lab and servicing area.

 
- Read full profile -

Wal-Mart Eagle River

Eagle River, AK

This was a Design/Build competition to build a retail store for Wal-Mart. Wal-Mart had been trying to build on their site for three years but encountered a substantial opposition from the surrounding Eagle River Community.

 
- Read full profile -

AAFES Joint Military Mall

Anchorage, AK

This was a Fast Track Design/Build project. Construction is concrete tilt-up and steel. The end result is 330,000 square feet of building, 7.6 acres of floor, 7.6 acres of roof and one million square feet of paving all designed and constructed in under seventeen months...

 
- Read full profile -

Mountain View Community Center

Anchorage, AK

Mountain View Community Center Design/Build is a community center in the truest sense of tradition. Set in the middle of Mountain View, in an established Anchorage neighborhood, the center serves the rich cultural diversity that is found only in this part of the city.

 
- Read full profile -

Alaska Regional Hospital Campus

Anchorage, AK

Alaska Regional Medical Office Building West - Design/Build three story medical office building consisting of approximately 50,000 square feet located on the campus. Tenant improvements were built out as the doctors leased the space.

 
- Read full profile -

Ernie Turner Alcoholism Recovery Center

Anchorage, AK

This is a Design/Build project completed in six months from design through completion of the construction. It is a 13,600 square foot, two story structure on masonry walls.

 
- Read full profile -

Office of Health & Human Services

Anchorage, AK

This was a new office complex required by GSA for Health and Human Services in Anchorage, Alaska. It consisted of a 21,566 square foot wood frame building erected on a 12 inch floating mass slab.

 
- Read full profile -

New Williwaw Elementary School

Anchorage, AK

This was a unique project for the Anchorage School District: to purchase a new fifteen acre location and build a 56,000 square foot twenty-six classroom elementary school in Anchorage.

 
- Read full profile -

Bering Strait School District

Anchorage, AK

Gambell K-12 School - This Design/Build project called for the addition of 32,000 square feet of new construction to the existing 11,000 square foot High School. The extreme weather conditions, the worst Alaska has to offer, required an innovative approach to a fast track enclosure of the structure.

 
- Read full profile -

Anchorage Water & Wastewater Headquarters

Anchorage, AK

The complete renovation of the AWWU headquarters building located at 3000 Arctic Blvd, in Anchorage, Alaska totaled 41,500 square feet. Included was a 6,200 square foot addition to the building.

 
- Read full profile -

Anchorage City Hall, Hill Building Renovation

Anchorage, AK

This project was the complete gutting and renovation of the Anchorage City Hall. This 144,000 square foot building was retrofitted with a concrete ductile moment frame to meet all seismic requirements of the 1991 Uniform Building Code.

 
- Read full profile -

Veterans Administration Outpatient Clinic-Regional Offices

Anchorage, AK

This project, consisting of approximately 204,000 square feet, is a Design/Build lease back competition. The award was made in September of 1990 and construction was scheduled to begin in April 1991 with completion in December 1991, utilizing fast track construction methods.

 
- Read full profile -

Benson Benny School

Anchorage, AK

Neeser Construction, Inc. accomplished substantial completion of the Benny Benson School on March 17, 1991. This was a 30,000 square foot slab on a grade wood frame building, with "hi-tech" sophisticated mechanical and electrical systems.

 
- Read full profile -

Military Entrance Processing Station

Anchorage, AK

Design/Construction of a 40,000 square foot two story steel and concrete commercial office building.

 
- Read full profile -

Yukon Flats School District

Fort Yukon, AK

The Venetie School Addition/Remodel project consists of a 16,000 square foot addition to the existing BIA School in Venetie, Alaska.

 
- Read full profile -