This contract consists of the removal of existing 8″ concrete (CN) sewer pipe and replacement with approximately 416 linear feet of Contractor furnished and installed 8-inch PVC pipe, and rehabilitation of 5 CMP manholes with contractor furnished and installed fiberglass manhole inserts, frames, and watertight covers. The work also includes installation and removal of temporary fencing; restoration of staging and disturbed wetland areas; and creek diversion and restoration.